The science teacher asked the students of Class-VIII to make a project report on pollution. when 10 students work on it the works get finished in 3 days how many students are required so that the work finishes in 2 days?
Answers
Answered by
6
3Days = 10 students
1 day = 10*3 students
2 days = 10*3/2
2 days = 15 students
Mark as branliest and follow me please