The science teacher asked the students of Class-VIII to make a project report on pollution. when 10 students work on it the works get finished in 3 days how many students are required so that the work finishes in 2 days? ​

Answers

Answered by sneeta386
6

3Days = 10 students

1 day = 10*3 students

2 days = 10*3/2

2 days = 15 students