the science teacher vs student of class 7 to make a project report on pollution when student work on it get finished three days how many student required so that work finished in 2 days
Answers
Answered by
1
Answer:
Answer:
15 students completes the work in 2 days.
Step-by-step explanation:
Given Problem is of inverse proportion as no of student increase result in decrease of day to finish the work.
No of Student required to a work in 3 days = 10
let No of Student required to a work in 2 days = x
Condition for inverse proportion is given by,
x_1\times y_1=x_2\times y_2x
1
×y
1
=x
2
×y
2
10 × 3 = x × 2
30 = x × 2
x = 15
Therefore, 15 students completes the work in 2 days.
Step-by-step explanation:
follow please
Answered by
0
Answer:
15 is right answer friend