the standard deviation of the critical pathis​

Answers

Answered by kingdg38
0

Explanation:

The standard deviation of the critical path is equal to the sum of the standard deviations of all of the activities on the critical path. FALSE The standard deviation of the critical path is equal to the square root of the sum of the variances of all of the activities on the critical path. 32.

Answered by AarnaThacharakkal
0

Answer: The standard deviation of the critical path is equal to the sum of the standard deviations of all of the activities on the critical path. FALSE The standard deviation of the critical path is equal to the square root of the sum of the variances of all of the activities on the critical path. 32.