Given : The standard hourly rate Is rs 1.40 the actual rate was rs 1.30 the labour rate variances was rs 600 favorable
To Find : the actual hours (AH)
A) 6000
B) 6400
C) 1000
D) 1500
Solution:
Let say actual hours (AH) = X
actual rate was rs 1.30
=> Actual Pay = 1.3X
standard hourly rate Is rs 1.40
=> Standard Pay = 1.4X
variances was rs 600
=> 1.4X - 1.3X = 600
=> 0.1X = 600
=> X = 6000
actual hours (AH) were 6000