The time (t) required to finish a certain job is inversely
proportional to the number of persons (p) on the job. If 10
persons can finish the job in 6 hours, how long will it take
for 30 persons to finish the job?​

Answers

Answered by MultiStan
2

Answer:

according to the question,

Time required to finish a job if the no.of ppl are 10= 6hrs

• • Time required to finish a job if the no.of people in 30= 6/10×30

=18 hrs