The time taken by 4 men to complete a job is double the time taken by 5 children to complete the same job. each man is twice as fast as woman. how long will 12 men, 10 children & 8 women take to complete a job, given that a child would finish the job in 20 days
Answers
Answer:
1 days
Step-by-step explanation:
Since, the time taken by 4 men to complete a job is double the time taken by 5 children to complete the same job.
Since, it is being given that;
1 child would finish the job in 20 days.
So, 5 child will complete it in 20/5 =4 days.
So, work done by 1 child in 1 day would be 1/20.
Since, it is being given that time by 4 men = 2 times time taken by 5 child.
So, work done by 4 men =
= 8 days.
So, work done by 1 men would be = 32 days.
So, work done by 1 man in 1 day would be 1/32.
Since, each man is twice as fast as woman.
So, the same work done by 1 woman would be days.
So, work done by 1 woman in 1 day would be 1/64.
So, total work done by all of them in one day would be:
1/20 + 1/32 /1/64 =
total work by 10 children would be 10/20 =1/2
total work by 12 men would be 12/32 = 3/8
total work by 8 women would be 8/64 = 1/8
total work by 10 children , 12 men, 8 women would be = 1/2 + 3/8 +1/8
= 8/8
= 1
So, total time would be 1 days.