The total wages of 6 men for 15 day work is Rs.23220. What will be the total wage of 15 men for 21 day work, if the additional 9 men take 3 times the wage than others?
Answers
Answer:
You can do like this
Step-by-step explanation:
Let the required wages be Rs. x.
More men, More wages (Direct Proportion)
Less days, Less wages (Direct Proportion)
Men 6: 9 : : 2100:x
Days 15:12
Therefore (6 x 15 x x) = (9 x 12 x 2100)
x = (9 x 12 x 2100)/(6 x 15) = 2520
Hence the required wages are Rs. 2520.
The total wage of 15 men for 21 day work, if the additional 9 men take 3 times the wage than others is Rs 130032
Given : The total wages of 6 men for 15 day work is Rs.23220
To Find : The total wage of 15 men for 21 day work, if the additional 9 men take 3 times the wage than others
Solution : The total wage of 15 men for 21 day work, if the additional 9 men take 3 times the wage than others is Rs 130032
It is given that the total wages of 6 men for 15 day work is Rs.23220
we have to find the total wage of 15 men for 21 day work, if the additional 9 men take 3 times the wage than others
Now
6 men wages for 15 day us Rs 23220
6 men wage for 1 day is
Since the additional 9 men take 3 times the wage than others
So ,
9 men wage for 1 day is × 3
6 men wages for 21 day (W1) is × 21 =
9 men wages for 21 day (W2) is × 21 × 3 =
So total wages of 15 men for 21 day is
W1 +W2
= +
=
= Rs 130032
So the total wage of 15 men for 21 day work, if the additional 9 men take 3 times the wage than others is Rs 130032
#SPJ2