Math, asked by rohangupta0424, 8 months ago

The work A can do in 20 days,B can do it in 12 days.After A having worked for some days B began to work in place of A,and the work was finished in 14 days.Find how many days A worked.

Answers

Answered by Palash221206
2

Answer:

Given,

A can do a work in 20 days.

=> In a single day, A will complete 1/20th part of the total work.

B can do a work in 12 days.

=> In a single day, B will complete 1/12th part of the total work.

So, if they both work together,

=> 1/20 + 1/12

=> 3/60 + 5/60

=> 8/60

=> 2/15

In a single day, A and B together will complete 2/15th part of the total work.

Now, let's move forward to what other things are given. A already worked for 5 days. So, the amount of work completed is

=> 5*(1/20)

=> 1/4.

As 1/4th of the work is already completed so now A and B have to complete the rest 3/4th of the work together. So, number of days required by both of them to complete the work will be

=> 1/((Work Left)*(Work completed in a single day))

=> 1/((3/4)*(2/15))

=> 1/(1/10)

=> 10 days.

The question is how long did the work last. As, A has already worked 5 days so the work lasted 5 days + 10 days = 15 days in total.

So, the correct answer will be 15 days.

Step-by-step explanation:

Answered by balasahebchikhale
0

Answer:

This is answer of question

Please mark me as brainly and give vote and give some thanks

Attachments:
Similar questions