There are 3 main steps of completion of a project- Development. Review and Roll out. After development, there are 4 people who can independently work and lead the process to the next step i.e. Review. Further ahead, there are 5 people who can work independently and lead to the next step i.e Roll-out. In how many ways can a project manager complete the project?
Answers
Answered by
22
Total number of Ways project manager can complete the project = 20 or 465 Ways
Step-by-step explanation:
After development, there are 4 people who can independently work and lead the process to the next step i.e. Review.
=> Project Manager can decide to have it done in 4 ways
Further ahead, there are 5 people who can work independently and lead to the next step i.e Roll-out.
=> Project Manager can decide to have it done in 5 ways
Total number of Ways = 4 * 5 = 20
if Project can be completed with any number of People
Then Review can be done in - ⁴C₁ + ⁴C₂ + ⁴C₃ + ⁴C₄
= 4 + 6 + 4 + 1
= 15 Ways
Then Roll out can be done in - ⁵C₁ + ⁵C₂ + ⁵C₃ + ⁵C₄ + ⁵C₅
= 5 + 10 + 10 + 5 + 1
= 31 Ways
Total number of Ways project manager can complete the project = 15 * 31 = 465 Ways
Answered by
1
Answer:
Step-by-step explanation: