There are 4 machines namely P, Q, R and S in a factory. P and Q running together can finish an order in 10 days. If R works twice as P and S works 1/3 as much as Q then the same order of work can be finished in 6 days. Find the time taken by P alone to complete the same order.
a) 11.5 days b) 12.5 days c) 13.5 days d) 14.5 days; There are 4 machines namely P, Q, R and S in a factory. P and Q running together can finish an order in 10 days. If R works twice as P and S works 1/3 as much as Q then the same order of work can be finished in 6 days. Find the time taken by P alone to complete the same order.; a) 11.5 days b) 12.5 days c) 13.5 days d) 14.5 days
Answers
Answered by
1
1/p+1/q=1/10
1/p= 1/10-1/q ------->(1)
given "R" works twice as "P"
so r's 1 day work= 2(1/p) ====> 2(1/10-1/q) ==> 1/5-2/q
"S" works 1/3 as much as "Q"
so s's 1 day work= 1/3(1/q)
r+s's 1 day work
1/5-2/q+1/3q=1/6
Solving this v ll get
q=50
substitute q=50 in eq(1)
v ll get
1/p=2/25
Therefore "P" ll finish the work alone in 25/2= 12.5 days
1/p= 1/10-1/q ------->(1)
given "R" works twice as "P"
so r's 1 day work= 2(1/p) ====> 2(1/10-1/q) ==> 1/5-2/q
"S" works 1/3 as much as "Q"
so s's 1 day work= 1/3(1/q)
r+s's 1 day work
1/5-2/q+1/3q=1/6
Solving this v ll get
q=50
substitute q=50 in eq(1)
v ll get
1/p=2/25
Therefore "P" ll finish the work alone in 25/2= 12.5 days
Answered by
1
Answer:
b) 12.5 days
Step-by-step explanation:
Let the total work be W, and the rates at which P and Q work be p and q work/day respectively.
Now, given:
Next, the rates at which R and S work are twice of P's and a third of Q's respectively, so,
Rate at which R works = 2p
Rate at which S works = q/3
Again, to complete the same work, they take 6 days, hence:
Equating:
, or,
Substituting in original equation, we get:
Using our analogy, P's rate of work per day is p, and let's say, it takes x days to complete the same work, so:
Comparing, we get, x = 12.5 days.
Similar questions