Math, asked by hemadurgarao4149, 10 months ago

Thirty men take 20 days to complete a job working 3 hours a day how many hours a day should 40 men work to complete the job in 18 days

Answers

Answered by sachin20051023
0

Answer:

40 men can complete the work In 4.444444444

Answered by yattipankaj20
0

2.5 hours

Step-by-step explanation:

30\times20\times3=1800 man has required to complete the job.

let x number of hours a day to do the same job

40\times18\times x=1800\\720x=1800\\x=\frac{5}{2}\\=2\frac{1}{2}

so,2.5 hours a day should 40 men work to complete the job in 18 days.