Thirty men take 20 days to complete a job working 9 hours a day. How many hours should 40 men work to complete that job in 20 days?
Answers
Answered by
0
Answer:
27÷4 or 6.75 hrs
Step-by-step explanation:
M×D×H=m×d×h
30×20×9=40×20×y
y=27÷4 or 6.75 hours