(This is a question from corporate finance)
You are helping a manufacturing firm decide whether it should invest in a new plant. The
initial investment is expected to be Rs. 50 crores, and the plant is expected to generate
after-tax cash flows of Rs. 5 crores for the next 20 years. An additional incremental investment of Rs. 20 crores will be needed to upgrade the plant in 10 years. If the discount
rate is 10%, estimate the net present value of the project.
Answers
Answered by
0
Answer:
I didn't get the question
Answered by
0
Net Present Value is Rs 4,45,93,088.40
Net present value is a capital budgeting measure used to assess a project's or investment's profitability. The difference between the present value of cash inflows and present value of cash withdrawals over a period of time is used to compute it.
NPV =
where.
Rt = Net cash flow
i = discount rate = 10% = 0.1
t = time period. = 20 years
Net Cash flow = - Initial Investment + Cash Flow - Incremental Inestment
∴ Rt = - 50 Crores + 5 × 20 Crores - 20 Crores
∴ Rt = 30 Crores
∴ NPV =
∴ NPV =
∴ NPV = Rs 4,45,93,088.40
Similar questions