Math, asked by gautamak, 1 year ago

This question has a lot of points so please answer!

If 10 people can do a piece of work in 5 days, working 2 hours a day, how long will 2 people take to do the same work, working 5 hours a day?

Please tell the answer with explanation and without explanation will be reported

Answers

Answered by siddhartharao77
1
Let the number of days be d.

Given that 10 people can do a piece of work in 5 days for working 2 hours a day.

We need to find out the number of days taken by 2 people working 5 hours a day to complete a work.


When this type of problems occur, we should use the following formula:

 \frac{m1 * t1}{w1} = \frac{m2 * t2}{w2}

 \frac{10 * 5 * 2}{1} = \frac{2 * 5 * d}{1}

100 = 10d

 \frac{100}{10} = d

d = 10.


Therefore the number of days required = 10.



Hope this helps!