this question of class 8.....
Answers
hey!
Let a complete work be as 1.
A complete work in 25 days,
So in 1 day, A do work = 1/25
B complete work in 20 days,
So in 1 day, B do work = 1/20
In 5 days both do work = 5*(1/25)+5*(1/20) = 1/5+1/4 = 9/20
So 9/20 work is completed in 5 days.
Now, remaining work=1–9/20 = 11/20
So B will complete work in = (11/20)/(1/20)=11 days
X can complete the remaining work in 13 3/4 days
Given:
X can do a piece of work in 25 days
Y can do a piece of work in 20 days
X and Y worked together for 5 days
After that Y leaved the work
To find:
In how many days X will complete the remaining work
Solution:
Given X can do a piece of work in 25 days
⇒ The work can be done by X in 1 day = 1/25
Y can do a piece of work in 20 days
⇒ The work can be done by Y in 1 day = 1/20
From above data,
The work can be done by X and Y together in 1 day =
Given that X and Y worked for 5 days
The work can be completed in 5 days = =
Remaining work will be = =
As we know X can do 1/25 of work in 1 day
Then number days to complete of work
= Remaining work / work done in 1 day = =
= 55/4 = 13 3/4 days
X can complete the remaining work in 13 3/4 days
#SPJ2