Math, asked by tapy12345, 9 months ago

three men A, B, C can complete a job in 8,12,16.A and B can work together in 3 days, then B leaves and c joins.In how many days A and C finish their work.​

Answers

Answered by Anonymous
0

Answer:

In 2 days A and C finish their job.

Step-by-step explanation: