Math, asked by AdhyayanDubey2601, 11 months ago

Three men do a job in 8 days . How long will 4 men take.To finish the job

Answers

Answered by Gangesh45
48

Answer:

Step-by-step explanation:

Time taken by three men = 8 days

Time taken by 1 man to finish the job =8×3 days (less men , more days)

Time taken by 4 men to finish the job = (8×3)÷4=6 days

Answered by samriddhi9468
1