Three painters can complete
a painting job in 24 days.
If 12 more painters join
the team 9 days after the
work has begun, how many
days would be required to
complete the job?
Answers
Answered by
6
Answer:
36 days is required to complete the job.
Thanks
Explanation:
Hope you like my answer