three painters completed 2/5 , 1/5 and 3/10 of a work each of three consecutive days . find out which painter did the most work in the three days .
Answers
Answered by
13
Answer:
Step-by-step explanation:
Three painters completed in consequence days = 2/5+1/5+3/10
=4+2+3/10 = 9/10
Total work =9/10
Therefore
Worker a 9/10-2/5=9-4/10=5/10
Worker b 9/10-1/5=9-2/10=7/10
Worker c 9/10-3/10=6/10
So here worker B complete 7/10th of painting work
Answered by
0
Step-by-step explanation:
Let first painter completed the work = 2/7
second painter completed the work = 1/5
third painter completed the work = 3/10
Therefore, LCM of 7,5 and 10 is 70
2/7 = 2×10/7×10 = 20/70
1/5 = 1×14/5×14 = 14/70
3/10 = 3×7/10×7 = 21/70
Therefore,21/70,20/70,14/70
Hence, the third painter did the most work in the three days.
Similar questions