English, asked by inshabilal6520, 1 year ago

Three person complete half of a work in 8 days if one of them discontinued working how many days would they take to do the remaining half

Answers

Answered by bestanswers
0

3 person complete 1/2 work in 8 days and full work in 16 days.


work done by 1 person in 1 day = 1/ ( 16 x 3 ) = 1/ 48.


work done by 2 person in 1 day = 1/ 24.


Time taken by 2 person to do full work is 24 days and 1/2 work is 12 days.

Answered by Arslankincsem
0

From the given question given to us,

Let us assume the total work to be x


Total work done by 3 people in 8 days is x/2


Total work done by 1 man in 1 day is equal to x/48  

The one man leaves. The total work done by him is x/6(x/48*8)

Therefore the time required to complete the remaining work by 7 people is  


X/6 + X/48 ×t + X/48 ×t = X

Once we solve this we get the answer to be 20 days.