Math, asked by sree1793, 1 year ago

three persons a ,b and c decide to work in such a way that a and c work together on 1st day ,b alone on 2 nd day , a and c on 3 rd and so on on alternate days .how many days will be required to complete the whole work if c and d alone finished the whole work in 20 days and 34 days respectively and b is 70% more efficient than D but 20% less efficient than A

Answers

Answered by abiramiragu
0

Answer:

Step-by-step explanation:

Total work to be done = LCM(6,8,12) = 24 units

A can do 4 units per day

B can do 3 units per day

C can do 2 units per day

B+C in 1 day = 5 units

for 2 days, 10 units will be completed by B and C.

Remaining is 14 units.

Now A and B work together, They can do 4+3 = 7 units per day.

Then 14 units will be completed in 2 days.


sree1793: Sir,please explain
Answered by karthikopositive
1

Answer:

14 (1/2) days

Step-by-step explanation:

work is done by B in = 100/170 * 34

                                =20 days

 work is done by A in = 100/80 * 20

                                     = 25 days

A=1/25: B=1/20: c=1/20.

1st day - A+C = 1/25 + 1/20 = 9/100

2nd day B = 1/20

so one pair of days work done = 9/100 + 1/20

                                                  = 14/100 = 7/50

7 pairs of days (or) 14 days of work done is = 7 * 7/50 = 49/50

Remaining work = 1 - 49/50

                           = 1/50

so 15 th days is A tern......

A's one day work 1/25

1/50 of work is done by A in = 1/50 * 25 = 1/2 days

total time taken 14 (1/2) days

Similar questions