Three persons named John, David and Robert, are hired to complete a piece of work John alone takes 8 days, David alone takes 12 days and Robert alone takes 16 days to complete the work. To start with, John works for 2 days and is then replaced by David. David works for 3 days and then replaced by Robert to complete the remaining work. If the total wages of John, David and Robert are $3000. then find johns wages for his work.
a. 850
b. 600
c. 900
d. 750
Answers
Answered by
0
The wage John receives for his work is 750.
Given:
John completers the work alone in 8 days.
David completers the work alone in 12 days.
Robert completers the work alone in 16 days.
Total wage is 3000.
Explanation:
Let the total work done be 1.
Work completed by John in 1 day is 1/8.
Work completed by David in 1 day is 1/12.
Work completed by Robert in 1 day is 1/16.
Let the remaining work done by Robert is 'x'.
Total work done by all is,
× + × + =
Solving above equation,
x =
Therefore, the work done by john is 25%.
The work done by David is also 25%.
The work done by Robert is 50%.
wage earned by John is 25% of 3000 = 750.
Thus, the wage earned by John is 750.
#SPJ2
Similar questions