Three persons P, Q and R can do a work in 40, 60 and 120 days respectively. But work in a pattern where only
one person works on the first day, only the second person on the second day and the only the third person on the
third day and so on the cycle continues. In how many days the work will be completed?
Cannot be determined
hi
48
36
DO
60
Answers
Answered by
0
Answer:
36. will be the answer I found it if not tell in the commrnt
Answered by
0
Answer:
Your answer is 36 please like me and follow me please