three pumps working 8 hours a day can empty a tank in 2days.How many hours a day must 4 pumps work to empty the tank in 1 day?
Answers
Answered by
1
Answer:
your answers is
4 pumps will take 4 hours to empty the tank in 1 day.
Answered by
0
total time taken to complete the work is 16 hrs as they completed it in 2 days working 8 hrs a day
now if 3 pumps can finish the work in 16 hrs
then they are finishing 1/16th of the work in 1 hour
so three pumps do 1/16th of it
then 1 pump does 1/48th of the work in 1 hr
so 4 pumps would do 1/12th of the work in 1 hr
thus it would take 12 hrs to finish the work if there are 4 pumps