Three spraying machines working together can finish painting a house in 60 minutes how long it will take for 5 machines of the same capacity to do the job?
Please solve step by step
Answers
Answered by
2
Answer:
Correct option is
A
36
Let the time taken by 5 spraying machines to finish a painting job be x minutes.
Number of machines 3 5
Time ( in minutes ) 60 x
Since, the number of spraying machines and the time taken by them to finish a painting job are in inverse variation, we have:
⇒ 3×60=5×x
⇒ 180=5x
⇒ x=
5
180
∴ x=36
∴ The required time will be 36 minutes.
Was this answer helpful?
Answered by
0
Answer:
36 mins
Step-by-step explanation:
3 Machines finish painting in 60 mins
1 Machine will finish painting in (60 × 3) = 180 mins (less machines, more time)
5 machines will finish painting in (180/5) = 36 mins (more machines, less time)
Ans - 5 machines will finish painting the house in 36 mins.
hope this helps...