Math, asked by singh1647, 3 months ago

Three typists working 8 hours a day type a document in 10 days. If only 2 typists are working, how many hours a day should they work to finish the job in 12 days ​

Answers

Answered by devarajak2008
0

Answer:

The job takes 3*8*10=240 typist-hours. 2 typists working x hours per day perform 2x typist-hours per day.