Math, asked by indusakesh17, 1 day ago

Three workers can finish the job in days. How many workers joined to the initial three workers after days if the job was done days earlier?

Answers

Answered by pratharshan8
9

Answer &

Explanation:

3 workers → 10days

after 2 days

3+x → d days

ATP,

x workers joined after 2 days and job was completed 2 days earlier. Therefore, total no. of working days d=6 days.

M1*D1=M2*D2

3*10=(3+x)*6

30=18+6x

12=6x

x=2

Hence, 2 workers joined after 2 days.