Math, asked by ishanchandel08, 1 month ago

Three workers Trump, Putin and Jinping are appointed to do a job. They together started the job but Jinping left after 3 days when 37% of the job was done. The remaining job was completed by Trump and Putin in 7 days. The ratio of efficiency of Trump and Putin is 4 : 5. Find the number of days required by the slowest worker to complete the entire job alone?

Answers

Answered by raj873719
0

Answer:

mark as brainleist..

Step-by-step explanation:

Attachments:
Similar questions