Time and work
A is thrice as good as B in work A is able to finish a job in 60 days less than B . They can finish the work in days if they work together .
tell the answer
Answers
Answered by
2
Answer:
22.5 Days
Step-by-step explanation:
A is 3 times efficient than B.
So if A can complete the work in x days, then B can complete the work in 3x days.
So 3x-x=2x= 60- days.
So x= 30 - days.
Therefore A can complete the work in= 30 days
And B can complete the work in 90 days.
So both together can complete the work in = (90 x 30)/(90+30)
= 2700/120
= 45/2
= 22.5 days