TIME AND WORK PROBLEM SUMS
Q. A certain number of labourers can complete levelling a road in 30 days. With 10 labourers less, the work was completed in 36 days. Find the original number of labourers.


Please help me out with this problem friends
And don't spam

Answers

Answered by aadivyraj
1

4 hours x 12 days=48 total hours worked

48 hours x 10 men=480 man/hours

1 man/480 total hours=1/480th of the work done per man per hour

8 x 6 x 1/480=1/10 work done per day

1 work / 1/10 work done per day=10 days necessary to finish the work

please mark me as brainlist