TIME AND WORK:-
we can see after 15 days of digging a Canal of 1200 length,3 by 4 part of the canal have been dug .Let's calculate how many days will be needed to dig the rest part .
Give correct answer
Answers
Answered by
12
Answer:
5 days
Step-by-step explanation:
3/4 part took 15 days .....
remaining 1/4 part takes 5 days