Time taken by a construction company to construct a flyover is a normal variate with mean 400 labour days and standard deviation of 100 labour days
Answers
Correct question is "Time taken by a construction company to construct a flyover is a normal variate with mean 400 labour days and a standard deviation of 100 labour days. If the company promises to construct the flyover in 450 days or less and agree to pay a penalty of Rs. 10,000 for each labour day spent in excess of 450. What is the probability that (i) the company pays a penalty of at least Rs. 2,00,000? (ii) the company takes at most 500 days to complete the flyover?"
Answer:
(i) The company pays a penalty of at least Rs. 2,00,000 is 0.242.
(ii) The company takes at most 500 days to complete the flyover 0.8413.
Step-by-step explanation:
Let X be the normal variate denoting the number of labour days. Given mean and s.d
(i) The company pays penalty of Rs. 2,00,000 at the rate of ₹ 10,000 per each extra labour day. No. of extra days =
So the probability that the company pays a penalty of at least Rs. 2,00,000 is probability that labour days should be at least
days, (i.e.) P () Now P(X ) = P(Z ≥ (470- 400)/100) = P(Z ) = 0.5 – P(0 Z 0.7) = 0.5 – 0.258 = 0.242
(ii)
Thus the probability that the company takes at most 500 days to complete the flyover is 0.8413.
This is a Mathematics problem of standard deviation related.