Math, asked by pinkesh2712, 1 year ago

Time taken by a construction company to construct a flyover is a normal variate with mean 400 labour days and standard deviation of 100 labour days

Answers

Answered by payalchatterje
0

Correct question is "Time taken by a construction company to construct a flyover is a normal variate with mean 400 labour days and a standard deviation of 100 labour days. If the company promises to construct the flyover in 450 days or less and agree to pay a penalty of Rs. 10,000 for each labour day spent in excess of 450. What is the probability that (i) the company pays a penalty of at least Rs. 2,00,000? (ii) the company takes at most 500 days to complete the flyover?"

Answer:

(i) The company pays a penalty of at least Rs. 2,00,000 is 0.242.

(ii) The company takes at most 500 days to complete the flyover 0.8413.

Step-by-step explanation:

Let X be the normal variate denoting the number of labour days. Given mean \mu = 400 and s.d \sigma = 100

(i) The company pays penalty of Rs. 2,00,000 at the rate of ₹ 10,000 per each extra labour day. No. of extra days =  \frac{200000}{10000}  = 20

So the probability that the company pays a penalty of at least Rs. 2,00,000 is probability that labour days should be at least

450 + 20 = 470

days, (i.e.) P (X \leqslant 400) Now P(X  \geqslant 470) = P(Z ≥ (470- 400)/100) = P(Z  \geqslant 0.7) = 0.5 – P(0  \leqslant Z  \leqslant 0.7) = 0.5 – 0.258 = 0.242

(ii)

P (X  \leqslant  500)   \\ =  P(Z  \leqslant   \frac{500 - 40}{100} ) \\  = P (Z  \leqslant 1)  P(Z \leqslant  1)  \\ = 0.5 + P (0  \leqslant  Z  \leqslant 1) \\  = 0.5 + 0.3413  \\ = 0.8413

Thus the probability that the company takes at most 500 days to complete the flyover is 0.8413.

This is a Mathematics problem of standard deviation related.

Know more about standard deviation:

https://brainly.in/question/35932722

https://brainly.in/question/50665860

Similar questions