To complete a task in 30 days a company needs
4 people each working for 7 hours per day
the company decides to have
5 people each working for 6 hours per day
assuming that each person works at the same rate, how many days will the task take to complete?

Answers

Answered by sahebabiswal27
1

Answer:

hope it helps

Step-by-step explanation:

15 days will take to complete the work