To complete a work, a company needs 5 more days than another company. If both of them work together it takes 6 days to complete it. How many days each company needs, if they do the work separately?
Answers
Answered by
14
Refer the attached image for the solution
HOPE IT HELPS !!!
Attachments:
Answered by
0
Step-by-step explanation:
hope it helps out u mate!☺