Math, asked by rishabh990, 10 months ago

to complete a work a takes 50% more time than B if together they take 18 days to complete the work then B takes the time to do the work in​

Answers

Answered by muhammedhashim2003
1

Answer:  30 days

Step-by-step explanation:

Ratio of time

A : B

3 : 2

[AB=150%100%=32]

efficiency of work =2:3(Efficiency is always inversely proportion to time)

Total work = 18days×(2+3) unit

= 90 units

B completes the work in

=90units3units/day= 30 days

^_^

Similar questions