to complete a work a takes 50% more time than B if together they take 18 days to complete the work then B takes the time to do the work in
Answers
Answered by
1
Answer: 30 days
Step-by-step explanation:
Ratio of time
A : B
3 : 2
[AB=150%100%=32]
efficiency of work =2:3(Efficiency is always inversely proportion to time)
Total work = 18days×(2+3) unit
= 90 units
B completes the work in
=90units3units/day= 30 days
^_^
Similar questions