Math, asked by Anonymous, 10 months ago

to complete a work a takes 50% more time than B if together they take take 18 days to complete the work how much time shall b take to do it​

Answers

Answered by MickeyandMinnie
1

Answer:

30 days

Step-by-step explanation:

here working A and B

A takes 50% more time than B

so

B=2A

A=B/2

together they take  18 days to complete

so here

Capacity Ratio will be  a:b=2:3

(a+b) 1 day work=1/18

Than b 1 day work portion =3/5*1/18

                                            =1/30

B can do --- 1/30 portion in 1 day

Than

whole or 1 portion in 30 days