To complete a work, A takes 50%more time than B. If together they take 18 days to complete the work,then how much time will B take to
do it?
(a) 30 days (b) 35 days
(c) 40 days
(d) 45 days
Answers
Answered by
1
Answer=30 days.
Step-by-step explanation:
The ratio between their times is:
A:B = 150 % / 100% = 3:2
efficiency of work =2:3(Efficiency is always inversely proportion to time).
So, total work = (18 days *2+3) units
= (18*5) units
= 90 units.
Then, B completes work in:
= 90 units/3 units per day
= 30 days.
Hence, the 30 days taken by B to complete work.