To complete a work, A takes 50% more time than B. If together
they takes 18 days to complete the work, then B takes the time to
dd the work in
Answers
Answered by
0
Answer:
i don't know
Step-by-step explanation:
nfdkeodoeowowkskwkqksksk
Answered by
66
AnswEr:
GivEn:
- A takes 50% more than B
- Work done together in 18 days
To Find:
- How much time B takes to do same work?
Solution:
According to Question,
Let assume B complete any work in x days.
Again,
A complete same work (x) in
✻ Work of both in 1 day =
After the cross Multiplication,
Thus,
B takes 30 days to complete the same work.