Math, asked by epicayu6283809, 1 month ago

To complete a work , a takes 50%more time than b . if together they take 18days to complete the work ,how much time shall b take to do it?​

Answers

Answered by likes24inanswer
2

Answer:

To complete a work, A takes 50% more time than B. If together they take 18 days to complete the work, how much time shall B take to do it ?

...

Correct Option: A.

⇒ x = 18 × 5 = 30 days

3

Answered by likes24inanswer
4

Answer:

To complete a work, A takes 50% more time than B. If together they take 18 days to complete the work, how much time shall B take to do it ?

...

Correct Option: A.

⇒ x = 18 × 5 = 30 days

3

Similar questions