to construct an embankment on a certain part of the river ichhamat, 40 laboursa are required to work for 35 days. if the work has to be finished in 28 days, let us find how many labour s will be needed
Answers
Answered by
0
Answer:
50
Step-by-step explanation:
Given,
40 men are required to work for 35 days.
we know,
work=men*hours*days
1 work=40 *35
if the work has to be finished in 28 days, let us find how many men will be needed
let x be men
1 work=28 *x
if work is same then,
40*35=28*x
x=50
Answered by
1
Answer:
Refer the above attachment.
I hope it's help you.
Attachments:
Similar questions
Math,
1 month ago
Computer Science,
1 month ago
Science,
3 months ago
Accountancy,
10 months ago
Hindi,
10 months ago
Social Sciences,
10 months ago