To do a certain work, A and B work on alternate days, with B beginning the work on the first day. If the work gets
completed in 22 2/3days, if A can finish the work alone in 48 days then B alone can finish 11 times the same work in:
Answers
Answer:
Step-by-step explanation:ate days, with B beginning the work on the first day. If the work gets
, A and B work on alternate days, with B beginning the work on the first day. If the work gets
completed in 22 2/3days, if A can finish the work alone in 48 days then B alone can finish 11 times the same work in:
Hold on, our servers are swamped. Wait for your answer to fully load.
completed in 22 2/3days, if A can finish the work alone in 48 days then B
o do a certain work, A and B work on alter, with B beginning the work on the first day. If the work gets
completed in 22 2/3days, if A can finish the work alone in 48 days then B alone can finish 11 times the same work in:
nate days, with B beginning the work on the first day. If the work gets
completed in 22 2/3days, if A can finish the work alone in 48 days then B alone can finish 11 times the same work in:
Answer:
27 days
Step-by-step explanation:
Let the efficiency of A be 1 unit
Total work = 48 x 1 = 48 units
Working alternatively,
Time for which A work in days = days
Work done by A = units
Time for which B work = 6 days
Work done by B = 48 - = units
Efficiency of B = 128/18 units per day
Time taken by B to finish 4 times the work = 192/(128/18) = 27 days