Together A & B can do a job in 16 days. A alone can do a job in 24 days. If they
worked together for 6 days & then B went away. How long did A take to
complete the unfinished part of the job?
Answers
Answered by
2
Answer:
A very easy and simple trick.
A+B=16 days
A=24 days
So, let's take LCM of 16 and 24. That's 48.
Notr: This 48 unit is the total work to be done.
So, A and B do (48/16) = 3 unit work/day …(1)
And, A does (48/24) = 2 unit work/day …(2)
Equation(1)-(2)
{A+B-A=3–2=1}
B does (3–2)= 1 unit/day
So, Total days required = (Total work)/(unit per day)
That is B can do it in (48/1)=48 days.
Thanks
Answered by
3
A + B complete work n 16 days
A + B complete 1/16 of work in 1 day
A completes work in 24 days
A completes 1/24 of work in 1 day
Subtract A’s work from A + B’s work to get B’s work in 1 day:
1/16 - 1/24
= 3/48 - 2/48
= 1/48 in 1 day
Therefore, it will take B 48 days to complete
Hence,the answer is 48 days.
❣Hope this helps you mate✌
Similar questions