Tom takes 18 days to finish a job. Mike is 20% more efficient than Tom. What number of days would Mike take to finish the job?
Answers
Answered by
3
Answer:
hii
your answer is here !
Step-by-step explanation:
Efficiency ratio of Mike to tom = 120:100 = 6:5
Let the number of days Mike takes be x. So,
6:5:: 18: x
x= 5 × (18/6)
No of days= (Efficiency of Tom × No of days Tom need)/ Efficiency of Mike
x= 15 days