Topic : Direct and indirect variations
Sohail can a piece of work in 15 days and sundar can do the same piece of work in 20 days. if they work on it together for 4 days , then what fraction of the work will left to complete.
Answers
Answered by
1
Answer:
The answer of the following question is 8/15 part.
Step-by-step explanation:
Let,
The whole work is 1 part.
Sohail alone,
In 15 days can do 1 part of work.
In 1 day can do 1/15 part of work.
Again, Sundar alone,
In 20 days can do 1 part of work.
In 1 day can do 1/20 part of work.
Therefore, In 1 day, they together can do 1/15+1/20 part or, 7/60 part of work.
In 1 day, they together can do 7/60 part of work.
In 4 days, they together can do (7/60)×4 part or, 7/15 part of work.
Therefore, (1-7/15) part or, 8/15 part of work will be left to complete. (Answer)