Given:

The cost incurred to date=Rs.1,20,000

Percentage of the work completed =60%

Work certified by Architect= 50%

To find:

Cost of work uncertified

Solution:

We can find the cost by following a few simple steps-

We know that the cost of uncertified work can be calculated by dividing the product of cost incurred to date and the percentage of uncertified work by the percentage of work done to date.

Cost of uncertified work= Cost incurred to date× percentage of work uncertified/ percentage of work done till date

The percentage of work uncertified= Percentage of work done till date- the percentage of work certified

=60%-50%

=10%

Using the information given, we get

Cost of uncertified work= 1,20,000×10/60

=2,000×10

=Rs.20,000

Therefore, the cost of work uncertified is Rs.20,000.