Twelve men are required to complete a work in 24 days. How many men are required to complete twice the work in 16 days

Answers

Answered by TooFree
14

Find number of days needed if the work is twice:

12 men takes 24 days to finish the work

12 men will need (24 x 2 = 48 days) to finish twice the work.

12 men needs 48 days

-

Find men needed for 1 day:

12 men : 48 days

12 x 48 men : 48 ÷ 48 day

576 men : 1 day

-

Find men needed for 16 days:

576 ÷ 16 : 1 x 16 days

36 men : 16 days

-

Answer: 36 men