Twelve men are required to complete a work in 24 days. How many men are required to complete twice the work in 16 days
Answers
Answered by
14
Find number of days needed if the work is twice:
12 men takes 24 days to finish the work
12 men will need (24 x 2 = 48 days) to finish twice the work.
12 men needs 48 days
-
Find men needed for 1 day:
12 men : 48 days
12 x 48 men : 48 ÷ 48 day
576 men : 1 day
-
Find men needed for 16 days:
576 ÷ 16 : 1 x 16 days
36 men : 16 days
-
Answer: 36 men