Math, asked by nirmalshrestha3207, 11 months ago

Twelve men can complete a job in 15 days. How many men will be required to finish the work in 9 days?

Answers

Answered by debtikadas98
1

Answer:

I think the required answer will be 6

Answered by chethanai
0

Step-by-step explanation:

12men: 15days

? :9 days

Cross multiply, .

12*9/15 = 108/15=7.2 approx