Twelve men can complete a job in 15 days. How many men will be required to finish the work in 9 days?
Answers
Answered by
1
Answer:
I think the required answer will be 6
Answered by
0
Step-by-step explanation:
12men: 15days
? :9 days
Cross multiply, .
12*9/15 = 108/15=7.2 approx