Math, asked by ariflohardaga, 8 months ago


• Twelve men can complete a job in 15 days. How many men will be required to finish the
work in 9 days?​

Answers

Answered by Anonymous
12

15days=12mens

so,1day=12/15men

that's why 9day=12/15 *9=7.2 answer

Answered by saisha2492006
3

12 men= 15 days

x= 9 days

\frac{12}{15} = \frac{x}{9}

U have to cross multiply.

\frac{12*9}{15*x}

x= \frac{12*9}{15}

x= 7.5 men

U will get answer is decimal but as people can't be in decimal. U can atlast write 7 men.

HOPE THIS MAKES UR DAY BETTER!

KEEP SMILING, KEEP SHINING!!

IF THIS HELPED U PLZZ MARK IT AS BRAINLIEST!