Twelve men can complete a work in 8 days. Three days after they started the work, 3 more men
joined. In how many days will they together complete the remaining work?
(A) 2
(B) 4
(C) 5
(D) 6
Answers
Answered by
1
let the efficiency of each men be 1
total work 12×8= 96
work done in 3 days 12×3 = 36
left work = 60
now total men 12+3 =15 men
days taken by 15 men to complete the remaining work= 60/15= 4 days (ans)
Answered by
1
Answer:
(c) 5
Step-by-step explanation: