Twelve men can complete a work in 8 days. Three days after they started the work, 3 more men joined them. In how many days will all of them together complete the remaining work ?
Answers
Answered by
0
=>12 ×3 = 15 × 5
=>X = 12/25
=>X = 12/25
Answered by
3
Answer:
4 days.
Step-by-step explanation:
Twelve men can complete a work in 8 days.
12 men 1 day work =
12 men 3 days work =
Remaining work =
After 3 days 3 more men joined them.
1 men 1 day work =
15 men 1 day work =
=
So, 15 men complete part of work in days = 1
15 men complete whole work in days =
15 men complete part of work in days =
=
So, they altogether complete remaining work in 4 days.